Lake Washington School District board to repurpose modernization funds for more classrooms, including permanent space at Redmond Elementary School

As the fastest-growing district in King County over the last two school years, Lake Washington School District is facing a need for classrooms to house its growing enrollment, which has increased close to 2,000 students over the last three years to 26,708. At the same time, the district completed all projects funded by the 2006 bond measure on time and under budget. It also received state construction assistance funds for those projects.

As the fastest-growing district in King County over the last two school years, Lake Washington School District is facing a need for classrooms to house its growing enrollment, which has increased close to 2,000 students over the last three years to 26,708. At the same time, the district completed all projects funded by the 2006 bond measure on time and under budget. It also received state construction assistance funds for those projects.

The district’s Board of Directors has proposed redirecting the remaining funds for additional projects. Projects include adding classroom space to meet the immediate needs of increased enrollment as well as planning for future construction projects such as new schools. More specifically, projects include purchase and installation of portable classrooms; adding permanent classroom space at Redmond Elementary School; modifying building interiors; remodeling, upgrading and equipping classrooms as necessary; acquiring land; and bond planning and pre-design. The district previously announced a plan to add 69 classrooms, which are included in the projects to be funded with these repurposed monies.

The 2006 bond measure authorized the issuance of $436 million of general obligation bonds. The bonds were used for Phase II of the district’s modernization program, which modernized 11 schools. In addition, one new school, Carson Elementary, was built. The district sold just over $423 million of the bonds over the next six years to complete the projects. The district estimates that even though not all of the bonds authorized were sold, it will still have approximately $12 million of unspent bond funds remaining.

In addition, the district anticipated receiving $23 million of state construction assistance funds for these projects. State funds are received after the projects are funded and completed. The district actually received $33 million in such funds. Three million of the funds were designated to pay interest on bonds that were issued in provide immediate funding for projects from the 2011 six-year Capital Projects Levy. (The levy funds are collected over six years: these bonds allowed the projects to be done before all the funding was collected.)

To use the unspent bond funds and unallocated state construction assistance funding on projects other than the already completed 2006 bond projects, the board held a public hearing at its Oct. 6 meeting. It must also adopt a resolution modifying the original bond resolution. The resolution has been placed on the Oct. 20 agenda.

Public comments on this redirection of funds are invited by the Board of Directors. Comments can be emailed to board@lwsd.org before the Oct. 20 meeting.